7. Delivery deadline, delay
7.1Particular delivery or performance deadlines
(period for performance) and dates specified
in our order are binding for the contractual
partner. The periods for performance start
from the date of the order. If periods or
schedules are specified in weeks or months,
then the latest completion date is the last
working day of the relevant calendar week
or month. When an agreed service or delivery
is to be provided "on call", then
the last working day of the week following
our call is the binding latest completion
date.
7.2 The period for performance is complied
with when the delivery or completion of
service at the place of performance and
transfer to us take place before the end
of the normal working period on the day
of the latest completion date. We are not
obliged to accept deliveries or services
outside normal working hours; if we do so,
the contractual partner has to bear any
additional costs we incur. When collection
by us has been agreed, we must be notified
that the goods are ready for dispatch at
least one day before the end of the period.
7.3 If the delivery period is not complied
with, without the delay being the responsibility
of the contractual partner, then we can
extend a period measured in months by one
additional month, otherwise by one additional
week, and cancel the contract if completion
does not take place within that period.
That does not apply if the reasons for the
delay are our responsibility.
7.4 If the contractual partner is late
with delivery, we have the right, without
prejudice to further legal claims, and without
further evidence to a delay penalty of 1%
of the value of the goods to be delivered
or services per complete week late, but
not more than 10%; the contractual partner
is entitled to show that we have suffered
less damage or none at all. We have the
right to withdraw from the contract without
setting a new completion date if, as a result
of a delay due to the contractual partner,
the delivery or service can no longer be
used by us as originally intended.
7.5 In all cases, the contractual partner
has the duty to notify us in writing without
delay and state the reason for probable
failure to comply with a completion date
as soon as this is recognisable for him.
If this notification is not made, by the
completion date at the latest, then the
failure to comply becomes the responsibility
of the contractual partner. At the same
time as the delay notification, the contractual
partner should set a new, certain completion
date. We are not obliged to agree to the
new date, but if we do so, the new date
becomes binding. Our further claims arising
from the delay remain thereby unaffected.